Construction Phases

The Approximate Build Process

Week 1 - 2

  • Erect scaffolding
  • Delivery of material
  • Install steel/ floor beams and skeleton of dormer
  • Measure for staircase
  • Building control inspection

Week 2 - 3

  • New staircase fitted
  • Meeting with manager to walk through and design layout of walls, doors, windows, electrical socket positions, radiator position and layout of bathroom suite
  • Client to order bathroom suite
  • First fix electrical and plumbing works carried out

Week 3 - 4

  • External roofing to be carried out along with window fitted
  • Fitting of insulation
  • Building contract inspection
  • Plasterboard & plastering

Week 4 - 5

  • Second fix electrical and plumbing works carried out
  • Wall & Floor tiling at client's request

Week 5 - 6

  • Second fix carpentry to be carried out
  • External snagging to roof works
  • Scaffolding dismantled

Week 7 - 8 (on larger project add 2 weeks)

  • Snagging & final touches to be carried out with a final clear up internally and externally
  • Final building control inspection
  • Handover package to client containing building control certificate, 10 years guarantee, part P electrical certificate and spare plans/ structural calculations.

Contact Us

For an obligation free consultation / survey and quotation please contact us below. Or email us from the our Contact page

Tel: 0800 689 5905
Email: info@penthouselofts.co.uk

Address:

Penthouse Lofts Ltd
137 - 139 High Street
Beckenham
BR3 1AG

© Copyright 2019 Penthouse LoftsWeb Design by Toolkit Websites